There is no function in MSP to specifically do this however you can set the deadline to be the same as the finish and then use Total Slack to see all the items which are driving the milestone. This will only show the critical path for the milestone. However if you set the deadline a long way in the past you will capture all the items as they’ll all be “critical”.
HTH
Miles