Home › Forums › Discussion › I Level Resources But they won't save! › Reply To: I Level Resources But they won't save!
When you have levelled the resources try making another change to the plan; add a dummy task at the end with no resource. See if this saves. If it does then you at least know that MSP is actually saving the plan and you only have to work out why levelling is being removed.