Reply To: Is there a way to update resource units more than one at a time?

Home Forums Discussion Is there a way to update resource units more than one at a time? Reply To: Is there a way to update resource units more than one at a time?

#416660
Larry Christofaro
Participant

Kim, you can use the Resource Usage view and add the Assignment Units field. There you can open all assignments for a resource, change the first assignment, and then drag that down to the other assignments. Be careful as the behavior of the task will depend on how the task is configured, in particular the Task Type field. Hope that helps…