Loading...
Quick Links

Reply To: Is there a way to update resource units more than one at a time?

Home Forums Discussion Is there a way to update resource units more than one at a time? Reply To: Is there a way to update resource units more than one at a time?

#416680
Larry ChristofaroLarry Christofaro
Participant

Sorry if the phrase task configuration was confusing. My intent was just how the task is defined/setup. Task Type and Effort Driven are the two primary fields that define how the task will behave if you make a change that affects one of the duration/effort/units triangle. For instance, if the task is fixed duration and you make a change to a resource units, then Project will change the resources work. If the task is fixed work and you make that same change, Project will change the duration. There are lots of explanations online if you want more understanding, including several MPUG articles. Hope that helps…