Reply To: Cascading

Home Forums Discussion Cascading Reply To: Cascading

#416701
Larry Christofaro
Participant

Hi Robert. It appears that the issue is not related to manually scheduled tasks since it works for others. Try looking at the Calculation option and make sure that project calculates after each edit. The option is in the Calculation section of the Schedule tab in Options. My guess is that somehow got set to Off. Hope that helps…