Home › Forums › Discussion › Resource calendar issues on Project professional › Reply To: Resource calendar issues on Project professional
Scott, I would suggest looking at two things. 1. Go to Options / General tab and set the Date format to include the time. 2. Look at the Options / Schedule tab and make sure that the Calendar options settings, specifically Hours per day matches the calendar. Hopefully that can help diagnose the issue.