Loading...
Quick Links

Reply To: Recalculation of actual duration and actual work (Project prof. 2016 stand alone

Home Forums Discussion Recalculation of actual duration and actual work (Project prof. 2016 stand alone Reply To: Recalculation of actual duration and actual work (Project prof. 2016 stand alone

#416780
Jigs GatonJigs Gaton
Member
  • Author
  • Forum Pro

Not sure I grasp the problem here, but I think it’s important to understand that Work and Duration are two different beasts in MSP. You can make the distinction in several ways within MSP. I’d first turn on the Work Column so you can see it, and then identify work done in the task details, as such:
https://www.projectplan365.com/wp-content/uploads/2019/11/Screenshot-2019-11-20-08.01.46.png