Reply To: Recalculation of actual duration and actual work (Project prof. 2016 stand alone

Home Forums Discussion Recalculation of actual duration and actual work (Project prof. 2016 stand alone Reply To: Recalculation of actual duration and actual work (Project prof. 2016 stand alone

#416783
Roger Heirbaut
Guest

Whatever tasktype I use (fixed work, fixed duration, fixed units), MSP always recalculates actual work when I modify actual duration and vice versa. Also tried making the task manually scheduled, same problem. I do not succeed filling in the exact values for the finished job: 4 days, 40 hours instead of the originally planned 5 days, 40 hours.