Home › Forums › Discussion › Recalculation of actual duration and actual work (Project prof. 2016 stand alone › Reply To: Recalculation of actual duration and actual work (Project prof. 2016 stand alone
Roger, I did a test on your scenario. The only way you can see the Actual Work of 40Hrs and Duration of 4 Days is to use the Daily Hour Entry on the Task Usage Screen. Even if you enter 11 hours on the first day, 10 on the rest, you will get 41 hours worked in a 4 day duration. Remember to then indicate the task is 100% complete. You can enter in 100% or you can indicate the Remaining Hours is 0. Good Luck.