Home › Forums › Discussion › Recalculation of actual duration and actual work (Project prof. 2016 stand alone › Reply To: Recalculation of actual duration and actual work (Project prof. 2016 stand alone
You have o go to file/options/schedule, at the end you will find the Calculation Options for this project, here you have to unmark the updating task status updates resource status and actual costs are always calculated by project options.
then you can update the project moving forward I this way.
good look
Best Regards…
Frank