Reply To: Timeline Timescale setting in Project 2013?

Home Forums Discussion Timeline Timescale setting in Project 2013? Reply To: Timeline Timescale setting in Project 2013?

#417182
Amanda K
Guest

In response to Ian’s post, the option to adjust the timescale of your timeline is only available in the Project PROFESSIONAL version, and not in Standard. I have been doing extensive research trying to make it work and have decided to just create a custom timeline in MS Excel to suit this particular need.