Reply To: Co-Authoring in MS Professional and Integration w/ Planner

Home Forums Discussion Co-Authoring in MS Professional and Integration w/ Planner Reply To: Co-Authoring in MS Professional and Integration w/ Planner

#417202
Larry Christofaro
Participant

I have good news and bad news:
Bad news first. MS Project and Project Online doesn’t do co-authoring and doesn’t connect to Planner as you are thinking. All you can do is connect a task in Project to a Planner schedule.
Good news is that Microsoft now offers Project for the Web, which is more the solution you are asking for. It has co-authoring and the same functionality as Planner and more (so it replacing Planner). It doesn’t have the portfolio capability that Project Online has, at least out of the box, but is their future direction.
Hope that helps…