Hi Zack. It’s been a long time since I’ve used self-assign tasks so I don’t have a solid answer. Microsoft usually does a pretty good job of providing features but also the flexibility to allow the user to use them how they want. Unfortunately, unless you are missing something, that didn’t seem to happen with team assignments. What happens if you change a milestone task to a 1 day non-milestone, and maybe assign successors a Start-to-Start instead of a finish-to-start relationship? If this fixes the problem then I would have to assume that self-assign doesn’t work the way you would like with milestones. Hope that helps, and better yet hope that someone else might have a better answer…