Loading...
Quick Links

Reply To: Actual Cost Resource doesnt get updated based on % complete – Project 2013

Home Forums Discussion Actual Cost Resource doesnt get updated based on % complete – Project 2013 Reply To: Actual Cost Resource doesnt get updated based on % complete – Project 2013

#417364
Larry ChristofaroLarry Christofaro
Participant

Hi Gayathry, the behavior you are getting is by design. Best practice and Microsoft recommendation is not to combine cost and other resources on the same task because of the behavior differences. Hope that helps…