Thomas Boyle
Guest

Andrew,
If you open the Task Inspector pane as well (its default position is along the left side), then up to five “driving” predecessors for the selected task will be listed and hyperlinked. You can jump straight to any of these tasks by clicking the link. When you use this feature to drill-down through driving predecessor logic, MSP remembers your previous steps and presents a “Go back to” link to retrace your steps to the starting point.
Good luck, tom