Reply To: is there a “go to” or “jump to” command

Home Forums Discussion is there a “go to” or “jump to” command Reply To: is there a “go to” or “jump to” command

#417448
Larry Christofaro
Participant

Ah, nice conversation from all. That would be the Task Path option. While on a Gantt chart view, select Task Path from the Format menu. This shows you a full path of either driving and/or non-driving predecessors and successors. It is a view only option but hopefully will help.