Loading...
Quick Links

Reply To: How to remove linking between % complete and actuals?

Home Forums Discussion How to remove linking between % complete and actuals? Reply To: How to remove linking between % complete and actuals?

#417700
Daryl DefflerDaryl Deffler
Guest

Ruhe
The problem you’re encountering is created because you’re you’re only importing actual work, which is half the needed information. You also need to import remaining work estimates (if it will differ from what Project will calculate when after actual hours are applied).
If a task is estimated at 100 hours and you tell it 50 hours are complete, project will always see that as 50% complete. If, in your example, this task should only be represented as 30% complete, then that means there needs to be 100 hours of remaining work. When the remaining work is adjusted, then Project will adjust things like the %complete and variances accordingly.
hope that helps