Reply To: Microsoft Project Professional 2010 — Query

Home Forums Discussion Microsoft Project Professional 2010 — Query Reply To: Microsoft Project Professional 2010 — Query

#417711
Larry Christofaro
Participant

That helps. Concrete and bags, or anything on a per unit basis, can be tracked using Material resources. Use Material Label for the bags, Cu.m., etc., then update using the resource assignment work and actual work column (not the task column). For indicating a status different than the calculated status you can use the Physical % Complete column. Hope that helps…