Reply To: tasks interdependence-MS Project 2016

Home Forums Discussion tasks interdependence-MS Project 2016 Reply To: tasks interdependence-MS Project 2016

#417712
Daryl DefflerDaryl Deffler
Guest

Stergios
Try making the dependency relationship Start-Start and also add a positive Lag value. Meaning, you could link Task B as the predecessor to Task A the successor with a Start Start relationship and add a +2D (plus two days) Lag value. This essentially says both A and B can start at the same time but delays the scheduled start of A (the successor) 2 days.

Just a thought.
Hope that helps.