Larry, I know how to use Bar Styles, but I didn’t understand what you meant by “Place the critical path step(s) after the conditional steps”.
What I did was create a formula for each flag on the task field in “Custom fields”, like this [Resource Names]=”LB Team 1″. And then I created a bar style for each of those flags.
The issue is that the bar style for these flags seems to have priority to the bar style for the critical tasks.
I’m sorry, it’s a bit difficult to explain 🙂