Guyathry, I mostly follow your question and believe you are mixing duration and work. You are setting remaining duration and then rescheduling work…?? I assume when you say reschedule the task you are using the reschedule remaining work option but that’s not obvious. Give that a test and let me know if that helps or if I’m missing something.