Reply To: Resource assigned shifts after status date while tracking in MSP

Home Forums Discussion Resource assigned shifts after status date while tracking in MSP Reply To: Resource assigned shifts after status date while tracking in MSP

#418255
Gayathry
Guest

Hello Larry,

Let me explain it further,
Activity A
Start Date – 1 Feb20
Finish Date – 6 Feb 20
Duration – 6Days
Resource – Work – 120 Hrs
My Resource spreads from 1 Feb 20 to 6 Feb 20 in Resource Usage sheet ie 20hrs for each day

Now i Fix Baseline,
Baseline Start Date – 1 Feb20
Baseline Finish Date – 6 Feb 20

Then I Set Status Date as 10 Feb 20 & Click Update Project using ” Rescheduling Uncompleted Task to Start after 10Feb 20 – For selected Task”

Now For Activity A, I give actual start as 1Feb 20 & Remaining Duaration as 3 Days
ie from status date of 10 Feb20 another 3 more days, software considers

Now ur Actual Start is 1 Feb 20 & Finish Column shows 13 Feb20 in Gant Chart Sheet

Now I go to Resource Usage sheet & Find all My resources that were spread from 1 Feb 20 to 6 Feb 20 before, has started only from 11 Feb 20 & got spread till 13 Feb 20 ie 3 days of remaining duration that was given.

Actually, the software should have taken the spread from 1 Feb 20 to 13 Feb 20, why didnt this happen

Now I guess I have put in detail.

S