#418322
Larry Christofaro
Participant

OK, create a custom flag field…call it Key Task or whatever makes sense. Then set the tasks you want to view with the Key Task custom flag set to Yes. Then create a filter that displays Key Task=Yes. If that’s still confusing then you might want to learn a bit about custom fields and filters. These are fairly basic Project functions and there are a lot of information online, including MPUG archive articles, that describe the functionality in detail. Hope that helps…