Reply To: “Move Incomplete Parts to Status Date” adds time constraint – sometimes

Home Forums Discussion “Move Incomplete Parts to Status Date” adds time constraint – sometimes Reply To: “Move Incomplete Parts to Status Date” adds time constraint – sometimes

#418334
Larry Christofaro
Participant

Dan, Project sets a SNET constraint when the entire task moves to a new date. Project sets the Resume date for tasks that have already started. Hope that helps…