Interesting…
Tom,
>>“Move Incomplete Parts to Status Date” – is a checkbox in the advanced calculation options with a default value of unchecked/false.
I don’t see that in my MS Project Pro 2016 instance. It has checkboxes like “Move end of completed parts after status date back to status date” and “Move start of remaining parts before status date forward to status date.” None of my calculation options are checked.
>>“Move Incomplete Parts to Status Date” will never impose a SNET constraint.
Mine certainly does. I think the dragons got me.
Thanks,
Dan