Larry,

Yes, maybe I’m trying too hard to circumvent using time constraints.

What I’m trying to do is schedule a task in the far future without a dependency chain or a constraint because 1) I can’t put together a full dependency chain yet but I’m sure it’ll happen sometime in November and 2) I stridently dislike time constraints. I thought I might be able to set a future start date without using either of those.

Any suggestions?
Dan