Reply To: “Move Incomplete Parts to Status Date” adds time constraint – sometimes

Home Forums Discussion “Move Incomplete Parts to Status Date” adds time constraint – sometimes Reply To: “Move Incomplete Parts to Status Date” adds time constraint – sometimes

#418350
Larry Christofaro
Participant

Ah…what’s the saying, using a sledgehammer to pound a nail? Project will by nature place a task as early as possible unless you place it somewhere else, and if you do that it uses a constraint. You could:
* Set them as a manually scheduled task until you know more
* Place them under a summary task that has a constraint (they would all have to be together)
* Hide the Gantt bar (if it’s the Gantt chart that is you primary concern). The option is a column and on the General tab of the task information.
* Still use a constraint until the task is setup properly
I’m sure there are other options depending on your priority, and Tom may have other thoughts. Good luck…