Larry Christofaro
Participant

Robert: Priorities are only used for the resource leveling feature. I’m not sure if that is part of the issue as it is not stated in the question. A couple of considerations if you are using resource leveling: For priorities to have an effect, you need to set the Priority order to Priority, Standard. Also, priority 1000 is unique in that it tells the leveling engine that this task is not to move. Hope that helps…