Reply To: Total Slack error when project finish date does not equal deadline

Home Forums Discussion Total Slack error when project finish date does not equal deadline Reply To: Total Slack error when project finish date does not equal deadline

#418433
Thomas Boyle
Guest

Meg,

It looks like you’ve done your research and drawn the right conclusions.

This is normal behavior for the critical path method, where deadlines or other late constraints (like FNLT) on the last task only become effective (controlling the late date of the task) when the task’s early finish date slips past the constraint date. As you have suggested, it is not uncommon to apply a paired SNET constraint and Deadline to the final delivery milestone – this forces the milestone’s scheduled (early) date to equal the contract date. An alternate approach is to split the milestone into two: Forecast Delivery, which is the unconstrained terminus of the project network; and Contract Delivery, hard-constrained (MSO) to the contract date and an FS successor to the Forecast Delivery milestone. Both of these approaches create positive total slack/float throughout the rest of the project as long as the project is ahead of schedule, with slack/float turning negative when the forecast slips past the contract date. This kind of behavior is presumed in a couple of the DCMA 14-point assessment metrics.

One key outcome of using either of these approaches is that the project float (also called terminal float, which is the difference between your current forecast date and the contract date) is folded into the network float (what you see now); blurring any distinction between them. [Actually, these practices are so common that I’d guess 90 out of 100 forensic schedulers would not recognize the distinction, either.] While there is general acceptance that network float is a shared resource available to both you and your customer (and other project stakeholders), there is no such general acceptance regarding project/terminal float. In fact, some contract forms explicitly reserve terminal float to the contractor as a risk-management buffer. Depending on the applicable contract forms and terms – particularly shared-float provisions, your schedule risk may be affected. Be sure to review them.

Good luck, tom