Home Forums Discussion “Contacting the server for information” when opening from SharePoint Reply To: “Contacting the server for information” when opening from SharePoint

#418488
Jigs Gaton
Member
  • Author
  • Forum Pro

Hi Dan, I am assuming you are using MSP Pro client to try? Since the “Can’t say master project anymore” and associated sub-project locations are coded into the project, that’s what I would check first, if you can get the main file to open again, you can bring up the link info and check it. But the 10% success rate may indicate something else, perhaps a slow connection or malfunctioning server on the host side. Well, there’s two ideas… best, Jigs