Guy, a master project does use its own bar definitions. Hence, you are required to put each bar definition of your 6 projects into the master as well (e.g. Flag1 = Yes for Project1 to make its bars appear green etc.)

Like that I manage to look at several projects in one view being color coded.
Let me know if you require further assistance.