Home Forums Discussion When does baselining NOT remove start and finish variances? Reply To: When does baselining NOT remove start and finish variances?

#418604
Larry Christofaro
Participant

Dan, instead of saving selected tasks try doing a complete baseline to baseline1 again (rebaseline Baseline1).