Home › Forums › Discussion › When does baselining NOT remove start and finish variances? › Reply To: When does baselining NOT remove start and finish variances?
>>You can copy a baseline to any other baseline by using the Set Interim Plan option within the Set Baseline dialog. For your question above, select Baseline in the Copy field and Baseline’n’ in the Into field. Good luck…
That is truly inspired UI design! That would have never occurred to me in a millennium. Thank you!
FYI, baselines for inactivated tasks are not saved to the destination when doing this.