Daryl DefflerDaryl Deffler
Guest

Griffin
Not sure what the question is, but I’ll assume its how to do this.
Define your normal work calendar, for example, M-F 8-5. Make that the project calendar and by default, Task B will use that calendar since you didn’t override it at the task level.
Create a 24×7 calendar and on Task A, attach that 24×7 calendar to that task.

Hope that helps