Home › Forums › Discussion › New tasks being created with zero slack – why might that happen? › Reply To: New tasks being created with zero slack – why might that happen?
Dan, just a guess, but is the “Calculate multiple float paths” advanced option checkbox checked for some subprojects and not for others? If the checkbox is checked, then incomplete tasks lacking successors normally get a total slack of zero. If it is unchecked, then the total slack will be the difference between the task’s early finish and the early finish of the last task in the (sub)project.