Thomas Boyle
Guest

Short answer: NO; logic on summary tasks is generally considered poor practice.

(If you are an expert and will not be communicating your schedule to others, then it is possible to link summary tasks together without ill effects, though disciplined adherence to a rigid set of scheduling protocols is required. Overall, the limited benefits of such an approach is not worth the potential hazards, which generally involve non-transparent – sometimes circular – logic flow.)