Loading...
Quick Links

Reply To: Why might my critical path be disappearing

Home Forums Discussion Why might my critical path be disappearing Reply To: Why might my critical path be disappearing

#454961
Daryl DefflerDaryl Deffler
Guest

Dan
I don’t know that I can provide an answer yet but here are a few questions that might help anyone wishing to chime in.
1) Is your schedule set up to automatically reschedule tasks when a change is made?
2) Did you re-level the schedule after the change?
3) Did you make any other schedule changes at the same time, for example shifting work from one resource to another, increasing assignment units, etc.
4) Are you scheduling current date to end of project (forward) and not end of schedule to current date (backward)?
5) Did the critical path re-route to another task sequence or simply disappear?
6) Did you break any dependency links between tasks on the critical path?
Some of these question may also hint at something to look at in the schedule and indirectly provide an answer.
hope this helps start the discussion