Reply To: Why might my critical path be disappearing

Home Forums Discussion Why might my critical path be disappearing Reply To: Why might my critical path be disappearing

#455484

Tom,

Apologies if this is a duplicate post. I’d swear I replied earlier but I see no trace of it.

>>I remember being a fan of fixed-duration tasks when I started using MP for hard project scheduling, having had some years of P3 experience prior. Over time, however, the love faded.

I was originally a fan of fixed unit tasks but Oliver Gildersleeve’s https://www.mpug.com/webnlearn-update-better/ webinar convinced me to favor fixed duration. Should I conclude from your comment above you’re now a fixed-units fan?