Reply To: Relation between Resource Max Units & Resource availability

Home Forums Discussion Relation between Resource Max Units & Resource availability Reply To: Relation between Resource Max Units & Resource availability

#464870
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Hi Koen, This should work. After changing the system date and opening Project, check Current Date in Project > Project Information. Max Units knows today’s date from Current Date field.