Loading...
Quick Links

Reply To: Copy activities from one project to another

Home Forums Discussion Copy activities from one project to another Reply To: Copy activities from one project to another

#472602
Jigs GatonJigs Gaton
Member
  • Author
  • Forum Pro

Hi Varun, if I understand what u are trying to do, I’d say stop cutting and pasting! That only preserves what you see during the cut, if I recall.

So, for a 28,000 activities schedule, that should be a master plan that imbeds a subproject of 19,000 activities stored in another file. 9,000 activities are in the Master Project, and 19,000 are in the Sub Project, just to be clear.

I wrote up the detailed cut and paste procedure once… but alas, it was a different time 🙂 But its not hard, starting with the original plan, dup that, cut them up in the correct proportions, then imbed the sub into the master – done!