Reply To: Baseline dates

Home Forums Discussion Baseline dates Reply To: Baseline dates

#472955
Thomas Boyle
Guest

Rena,
I’d suggest manually de-progressing a copy of the current schedule, baselining it, then re-progressing the schedule either manually or via xml import (the latter doesn’t always work.) As Larry points out, the visible baseline task cells can be manually modified (e.g. via copy/paste), but you would also need to modify all the assignment and time-scaled data, which is quite tedious and error-prone. Good luck, tom