Reply To: How to move linked .mpp files?

Home Forums Discussion How to move linked .mpp files? Reply To: How to move linked .mpp files?

#478408
Larry ChristofaroLarry Christofaro
Participant

BobC, good question. Go ahead and move the projects and resource pool to the new location. Then do the following:
* Open the resource pool and all projects you want to link (or a few at at time)
* Select Resource Pool / Share Resources, select each of the existing links and break the link
* Open each project you want to link, select Share Resources, and reselect the resource pool
Hope this helps…