The first thing I always check when I see that is to look for tasks which have fractions of days. For example if a task is set for 1.5 days, it will start on Monday and finish on Tuesday, but the successor will also start on the Tuesday (12:00pm).

If you format your dates to include times (i.e. Dec 14 2020 8:00am) like what Daryl said above, you can quickly check to see where this might have accidentally happened.

-Bob C