Guy;
MS Project supports something called “Hammock Tasks” where the duration of one task is dependent on other tasks. I found this MPUG article which may help.
Not sure if this is exactly what you’re looking for.

Do’s and Don’ts: Using Hammock Tasks

Hope this helps