Reply To: Project task summary

Home Forums Discussion Project task summary Reply To: Project task summary

#479415
Jigs GatonJigs Gaton
Member
  • Author
  • Forum Pro

Hi Rosie! Those are calculated from the tasks below, within the summary, and should not be changed. They can be hidden, but manually typing within those cells will mess things up for an automatically-scheduled sheet.