I’m a fan of Ceptah Bridge. I’ve never used “The Connector”. I don’t even recall whether I evaluated The Connector an the time. One of my criteria was that I didn’t want to have to engage with IT or a Jira Admin and the cost of Ceptah was also reasonable enough that I didn’t have to make a huge case for getting it.