Reply To: Project 2010 View of Predecessors and Successors

Home Forums Discussion Project 2010 View of Predecessors and Successors Reply To: Project 2010 View of Predecessors and Successors

#73452
James
Guest

Hi Paul,
While in Gantt chart view, you can choose Details and then show the Task form at the bottom. In the task form you can choose(right click) to show predecessors and successors. As you scroll through the tasks in the Gantt chart, the corresponding predecessor and successor tasks shows up in the Task form.

Not sure if this is what you want, but it helps to review the schedule for me.