Haseeb – Add the resource, say “Fuel”, as material resource in Resource Sheet view. Record the unit price in Std. Rate column, say $1.00. Now double click the summary task (not to Project summary), and in Resources tab of Task Information dialog, assign the Fuel resource with Units as 1/d ; 1 unit of Fuel is consumed every day. In Gantt Chart, insert Cost column to see the total cost of Fuel from begin till end of summary task,