Paul – I agree with James on using Task Form. If you need something graphical, you can use Relationship diagram. Once you split the view, change the Details from Task Form to Relationship diagram (using More views). The relationship diagram will display the selected task in the middle with its immediate predecessor(s) and successor(s) to its left and right as boxes.