Reply To: AUTOMATIC SCHEDULE

Home Forums Discussion AUTOMATIC SCHEDULE Reply To: AUTOMATIC SCHEDULE

#77590
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Fabio – Task mode feature was introduced in Project 2010. Using this feature you can ask Project to calculate automatically or not (you can insert a column Task Mode). If you open project file created in Project 2007 or earlier version, Task mode is not supported and hence you see these buttons are disabled and also on the title of Project will be something like FileName[Compatibility Mode]. To get this right, save the file in Project 2010 format to support this feature.